Projet d’extension du champ pétrolier nord du Qatar
– postes d’amarrage 7, 8, 9 et 10

 

CHANGEMENT DE GÉOMÉTRIE DE LA CHAUSSÉE ET OPTIMISATION DES BLOCS (POSTE 8, 9 ET 10)

 

Each of the new LNG Berth comprise the following main marine works elements:
• Minor dredging works for the rock foundation.
• Connecting causeway – between existing main breakwater and loading platform – shall be designed as a rock fill embankment.
• Loading platform, size 36m x 33.5m – shall be designed as a reinforced concrete deck with an unreinforced gravity concrete block wall
• 4No. Breasting dolphins with mooring and breasting furniture, size 12m x 10.4m – shall be designed as reinforced gravity concrete block dolphins

• 8No. Mooring dolphins with mooring furniture, size 11m x 8.5m – shall be designed as reinforced (bottom blocks) and un-reinforced gravity concrete block dolphins
• Interconnecting walkways, 320m x 2m
• Flare support piled substructure, 11m x
8.5m
• Topside mechanical, electrical, piping and
instrumentation equipment – by SCT
• Road works – by SCT
• QRH–bySCT
• Buildings – by SCT

MAIN QUANTITIES (for Berth 8, 9 & 10)

Dredging : 28,423 m3
Rock : 3,421,412 ton
Structural fill : 85,743 m3
Geotextile : 91,962 m2
PC concrete blocks : 74,874 m3 (2,574 nrs)

Concrete : 20,295 m3
Catwalk : 522 ton
Tubular pile : 202 ton

Project information

Project name
EPCC for the Onshore Off plot Common Lean LNG Storage and Loading Facilities for the North Field Expansion – Package 2 Project No. LTC/C/NFE/3997/18
Subcontract for Marine Works for Berth 7, 8,9 & 10

Client
Qatar Petroleum (représenté par Qatargas Operating Co. Ltd.)

 

Entrepreneur principal
Samsung C&T

 

Emplacement
Cité industrielle de Ras Laffan, État du Qatar

 

Valeur du projet
Montant total 240 455 741 USD
Postes d’amarrage 8 et 9 : 123 212 182
USD Poste d’amarrage 10 : 57 977 659 USD
Poste d’amarrage 7 : 59 265 900 USD

Date de début
mars 2021

 

Date d’achèvement
février 2025

 

Partenaire(s) JV

 

Partie MIC
à 100%